Problem Statement: The challenging enquiry of transporting 200 nos of Nacelle & Hub from Chennai to Bhuj-GJ (2,500 KMs by road) in a stipulated period of 3 months, had the lesser possibility to complete the movement by road in given time. The estimated turnaround time per transit by road was 30 and 20 days for Nacelle and Hub respectively.

Solution
: A well-calculated proposal of executing the stated movement in multimodal transportation of road and coastal in multiple voyages made the service more viable with utmost efficiency.

Pre-Carriage: Mamandur to Chennai Port
Carriage: Chennai Port to Kandla Port
On-Carriage: Kandla Port to Bhuj (GJ) sites/wind farm

Customer Benefits
:

  • Reduction in cost.
  • On-time delivery.
  • Avoided the possible transit damage which happens via road.
  • Quality in execution along with the timely update on the movement.